Smappee Infinity – Installation manual – English Page 9 of 29
4. Planning and site preparation
The first step is to determine the complete monitoring solution. This consists of listing all
the loads that need to be measured, their properties, and the required hardware (Smappee
and others).
The checklist provided helps you to determine all necessary technical information for the
next steps and also to collect all the necessary hardware.
General architecture - what is to be monitored
Single or multiple metering locations: Where are the fuse boxes or appliances to be
monitored? (Location inside the building, distances between them, etc.)
Total load (main service): Yes/no?
Specific appliances? (e.g. HVAC, Heat pump, EV, Solar, etc.). Are they fused separately or
are they powered by a wall socket & plug?
Circuits (main sockets, lighting area, etc.)
Details
Topology: Verify the mains voltage – single phase (1P), three-phase 3P+N (3*400) or 3P
(3*230)
How are the total load, solar, circuits, and/or appliances fused?
Phases of each measured load (circuits and appliances): Single-phase, three-phase,
3P+N (3*400V) or 3P (3*230V), voltage, frequency, power, amps
Cross-sectional area or diameter of the wiring
How will a stable internet connection be provided to the energy monitor: Wi-Fi, Ethernet,
or 3G/4G cellular network?
Tools (not included)
Multimeter
Screwdrivers
Wire stripper
Flashlight
Needle-nose pliers
Wire cutter
Optional: drill, drill bits and screws