NOTICE TO USER . . . . . . . . . . . . . . . . . . .2
SAFETY. . . . . . . . . . . . . . . . . . . . . . . . . . . .3
INSTALLATION
Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Preparation. . . . . . . . . . . . . . . . . . . . . . . . . 5
Mounting Methods . . . . . . . . . . . . . . . . . . . 5
Side Frames . . . . . . . . . . . . . . . . . . . . . . . . 6
Canopy Header . . . . . . . . . . . . . . . . . . . . . 8
Side Curtains . . . . . . . . . . . . . . . . . . . . . . 12
Weighted Seal, Wear Panel . . . . . . . . . . . 13
Bumpers . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Collapsible Style Draft Pad. . . . . . . . . . . . 17
MAINTENANCE . . . . . . . . . . . . . . . . . . . .19
PARTS
Exploded View – 620G. . . . . . . . . . . . . . . 20
Exploded View – 620NH. . . . . . . . . . . . . . 22
WARRANTY . . . . . . . . . . . . . . . . . . . . . . .24

Eclipse®Dock Shelter (620G, 620NH) Installation/Service/Owner's Manual Rite‑Hite®
2Publication: AMEN00141 2019-11-22
NOTICE TO USER
Thank you for purchasing a Rite‑Hite product.
The Eclipse®620G and 620NH Dock Shelters provide a
durable, eective environmental seal between the trailer
and building.
Instructions apply to both 620G and 620NH unless
otherwise noted.
The English version of this manual shall prevail over any
error in, or conicting interpretation of, any translations.
Rite‑Hite reserves the right to substitute and/or modify
parts and drawings. If separate prints are included with
the unit, they supersede the manual.
For best results, have this product serviced by an
authorized Rite‑Hite representative.
A Planned Maintenance Program (P.M.P.), customized to
your specic operation is available and recommended.
For a P.M.P., contact your local Rite‑Hite representative
or Rite‑Hite technical support at (U.S.) 1‑888‑456‑3625,
(S.A.) +55 21 99616 4421.
The Rite‑Hite products in this manual are covered by one or more of the
following U.S. patents: 6014844, 6044597, 6205721, 6233885, 7146673,
7185463, 7246467, 7287353, 7584517, 7695048, 7757442, 7877831,
7882663, 8042307, 8141305, 8156995, 8307588, 8327587, 8353136,
8458960, 8495838, 8540007, 8752335, 8800086, 8839842, 8887447,
8915029, 8943630, 8991467, 9003724, 9003725, 9010039, 9079713,
9162832, 9170044, 9187271, 9193543 9534372, 9534373, 9551181,
9592972, 9624049, 9751703, 9797127, 9797128 and may be covered
by additional pending U.S. and foreign patent applications.
Manufactured by Rite‑Hite Environmental Enclosure Corporation.

Rite‑Hite®Installation/Service/Owner's Manual Eclipse®Dock Shelter (620G, 620NH)
Publication: AMEN00141 2019-11-22 3
SAFETY
Safety Identifications
DANGER
Indicates a hazardous situation which, if not
avoided, will result in death or serious injury.
WARNING
Indicates a hazardous situation which, if not
avoided, could result in death or serious injury.
CAUTION
Indicates a hazardous situation which, if not
avoided, could result in minor or moderate injury.
NOTICE
Indicates a situation which can cause damage to the
equipment, personal property and/or the environment,
or cause the equipment to operate improperly.
NOTE:A note is used to inform you of important
installation, operation, or maintenance information.
Lockout Procedure
Barricade work area and post safety warnings.
Power supply and control must:
• Be disconnected or locked in OFF position
using a lockout device approved by local
codes.
• Have signage that;
−Clearly states repairs are being made.
− Identies person responsible for lockout condition.
NOTE:Only this person should be able to remove
warnings and lockout device.
−Withstands environmental conditions (weather,
wet, and damp, etc.) and remains readable.
General
WARNING
To prevent unauthorized use, barricade the work
area at dock and ground level while service work
is being performed.
190820

Eclipse®Dock Shelter (620G, 620NH) Installation/Service/Owner's Manual Rite‑Hite®
4Publication: AMEN00141 2019-11-22
INSTALLATION
Overview
1. Unpack and inspect unit.
2. Install side frames and bracket anchors.
3. Install side arms, front bar and canopy top.
4. Install side curtains and pocket straps.
5. Install gutter, roller seal, and wear panels.
6. Install draft pads.
Instructions assume that the installer is outside the building facing the loading dock.
Figure 1

Rite‑Hite®Installation/Service/Owner's Manual Eclipse®Dock Shelter (620G, 620NH)
Publication: AMEN00141 2019-11-22 5
INSTALLATION
Preparation
Verify all components were received. Notify your Rite‑Hite
Representative if parts are missing or damaged.
Mounting Methods
NOTE:Any additional fasteners, backer plates and
materials for additional structure are supplied by others.
Concrete Block or Brick Wall
Through bolt fastening is required.
• Bore a hole through the building wall.
• Use a 3/8in [9mm] diameter threaded rod with
a washer, nut, and jam nut on each end.
• Install a backer plate inside the building wall when
the wall will not support the bolt.
Concrete Tilt-Up Walls (Precast)
Use 3/8in [9mm] lag bolts with expansion shields,
3/8in [9mm] 1 piece anchor bolts with expansion collar, or
equivalent fastener.
If building wall is too thin to eectively hold the lag bolt or
anchor bolt, through bolt method of attachment is required.
NOTE:To determine anchor length, use anchor
manufacturer’s recommendation for minimum anchor
embedment.
Metal Sided Building
Through bolt fastening is required.
• Use a 3/8in [9mm] diameter bolt with a washer and
lock nut to fasten the unit to the structural member of
the building or to the backer plates. If necessary, use a
3/8in [9mm] diameter threaded rod with a washer and
lock nut on each end.
• Install a backer plate that is fastened directly to
structural member when it is not possible to fasten
directly to structural building members.
NOTE:See "Figure 2" for recommendations.
Uninsulated Wall Building
Building Structural Member
Filler Boards*
Min. 3/8in Fasteners*
Corrugated
Metal Siding
Head Frame
2x6 or Structural Steel Channel Backer
Angle Bracket*
Insulated Wall Building
Building Structural Member
Angle Bracket*
2x6 or Structural Steel Channel Backer*
Insulation
Filler Boards*
Head Frame
Pipe Spacers*
Corrugated
Metal Siding
Min. 3/8in Fasteners*
*Supplied by others.
Figure 2

Eclipse®Dock Shelter (620G, 620NH) Installation/Service/Owner's Manual Rite‑Hite®
6Publication: AMEN00141 2019-11-22
INSTALLATION
Side Frames
D
G
F
E
H
J
J
B
C
A
1. Before mounting side frames, install canopy mounting
brackets (A) to top of side frames (B).
• Position bracket so notches at top of bracket are
ush with the top of the wood, side pad backer (C).
• Secure in place with 6 hex head wood screws (J)
provided.
NOTE:Brackets (A) are not part of the overall unit
width. Unit width when mounting side frames should
be measured from outside edge of side frames.
Brackets add ≈ 1/4in [6mm] to unit's overall footprint.
Allowance is accounted for in the header installation.
2. Measure and mark:
• Measure dock door opening width (D). Divide in
half and mark the centerline of the opening at
dock level (E).
• Measure unit width and divide in half. Compare to
PAF (Product Application Form) specs.
• Measure from door centerline (E) to half of the head
frame dimension (F) and mark the outside wall (at
the bottom of the door opening or at dock level).
This mark is for the outside edge of the side frame.
• Measure (at dock level) from this mark (outside
edge of the side frame) across the door opening to
the unit width (G). Mark this measurement for the
outside edge of the second side frame.
• Consult PAF or sales representative for mounting
height to the bottom of the side pads (H). Measure
up from grade on the dock face and mark.
NOTE:Typically, the bottom of the side pad is
mounted at dock height. Some applications may
require mounting them at a dierent location.
Example: When dock bumpers are mounted
above dock height or above the pit oor (on vertical
leveler applications) it may be required to mount
the bottom of the side pads/side frames at a height
even with the top of the bumpers.
3. Dry fit and shim:
• Using carpenter’s level, plumb up the wall the height
of the side frame and mark the outside edges of the
side frames on the wall at top.
• Measure full width, etc. Using a plumb bob or
carpenter’s level make sure that the outside wall
is plumb from the highest point on the side frame
location to dock level.
• Shim side frames as required.
Figure 3

Rite‑Hite®Installation/Service/Owner's Manual Eclipse®Dock Shelter (620G, 620NH)
Publication: AMEN00141 2019-11-22 7
INSTALLATION
Side Frames Continued
Flush Mounting
Flush Mount
Bracket
Oset =
‑1/4in [‑6mm] to
1/4in [6mm]
‘L’ Bracket
Oset Mounting
‘L’ Bracket
Bent
‘L’ Bracket
Oset =
1/2in to 3 1/2in
[13mm ‑ 89mm]
‘L’ Bracket
‘L’ Bracket Oset =
4in [102mm] or
Greater
9in
[225mm] max.
Equal
9in
[225mm] max.
Equal
4. Install brackets:
NOTE:
– Side frames are supplied with brackets that
match the application (Figure 4).
– If blockouts were supplied with the unit,
reference the blockout installation manual
(Document 1321‑0008) and this manual to
ensure proper installation of the blockouts and
the side frames.
• Position the side frames on their marks.
• Mark the side frame for bracket installation (3 on
each side of each side pad) (Figure 5).
Example: Line up the mounting hole on the
bracket with a mortar joint on the wall and attach
the mounting bracket to the side frame backer
board.
• Attach the brackets to the side frame backer. Use
(supplied) 1/4in x 1 1/4in wood screws for wood
backers.
NOTICE
4in [102mm] width side frames require protective
bumpers to be installed below the side pads.
Reference "Bumpers" on page 17.
If the 4in [102mm] side frame (including blockout) has
an overall projection greater than 40in [1016mm], the
bottom, front of the blockout must be secured to either
the bumpers, the building foundation, or any other
solid rigid structure underneath the blockout. This is
required to stabilize the side frames.
5. Attach the side frames to the building wall, ensuring
they are aligned with the marks made in step 1.
NOTICE
It is critical to mount the side frames plumb and per
the building style (Mounting Methods, page 5).
Figure 4
Figure 5

Eclipse®Dock Shelter (620G, 620NH) Installation/Service/Owner's Manual Rite‑Hite®
8Publication: AMEN00141 2019-11-22
INSTALLATION
Canopy Header
NOTE:Installation procedure is the same for Standard
Pitch and Integral Hood, except that the canopy mounting
bracket is longer for the Integral Hood.
Side View
A
Bracket for Reference Only
Side Arm
Front Bar
1. Attach the side arms to the front bar. Before inserting
the attachment bolts, confirm orientation of the side
arms is correct (A).
C
B
2. Lift the side arm/front bar assembly together and
position across the installed side frames and
mounting brackets. Position it on top so the side arms
on the top frame are facing the wall and land between
the mounting brackets on side frames (Figure 7).
3. Connect bracket and side arm with bolt (B) on each
side of unit. Secure with (supplied) nylock nut (C).
D
E
4. Install the installation chains on both sides of the
canopy frame. The chains hold the front bar up so the
canopy cover can be attached.
• First attach quick link side (D) of the chains to the
inside legs of the canopy mounting brackets.
• Next, lift up canopy front bar and attach the "S" hook
side (E) of the chains to holes on the inside face of
the side arms.
Figure 6
Figure 7
Figure 8

Rite‑Hite®Installation/Service/Owner's Manual Eclipse®Dock Shelter (620G, 620NH)
Publication: AMEN00141 2019-11-22 9
INSTALLATION
Canopy Header Continued
Endcap Endcap
5. Unroll and then lift and lay the canopy cover (top bar
attached) on top of the side arms at the wall.
Lift up and slowly position the top bar behind the tabs
on the canopy mounting brackets.
Make sure the top bar is oriented correctly.
• All 4 faces of top bar should be covered with fabric.
• Fabric should be wrapped from front face of top bar,
under the bottom, up the back (against the wall),
across the top towards the front of the unit, then
extend from the top, front corner of the top bar down
to the front bar.
• The canopy cover and end caps (at the corners
where the canopy top and end cap meet) are laying
correctly over the edge of the mounting bracket.
6. Drape canopy cover over the front bar (the
2 1/2in [65mm] square tubing). Make sure the canopy
cover at the front corners lays correctly over the
corners of the front bar.
Side View
Part of End Cap
Removed for Clarity
Pocket with Poly
Notch
7. Wrap the canopy cover front bar pocket (with poly strip
inside), down and around the bottom of the front bar.
• The pocket/poly strip will wrap back up the back
inside face of the front bar and tuck behind the steel
angle welded at back.
• The pocket is notched to t around the side arm
bracket and the edge of the pocket should line up
with the edge of the steel angle on both ends about
1/2in [13mm] away from the side arm bracket. Make
sure that the pocket/poly strip combination gets
seated all the way down in the space between angle
and front bar.
Figure 9
Figure 10

Eclipse®Dock Shelter (620G, 620NH) Installation/Service/Owner's Manual Rite‑Hite®
10 Publication: AMEN00141 2019-11-22
INSTALLATION
Canopy Header Continued
WARNING
The canopy header is a self supporting unit.
Installing less than 6 anchors and/or insucient
anchor installation methods is dangerous and can
cause unit failure.
Metal sided buildings require special and
increased mounting support considerations.
1 anchor location is required into solid structure
(H) (Figure 11) on each side of the door opening.
All other mounting locations require a backer
plate and pipe spacers (as needed) on the inside
of the wall so the mounting bar and the wall will
ex together.
• If structure is not aligned with 1 of the
pre-drilled mounting holes. Drill new hole
which will replace the nearest pre-drilled
mounting hole.
• If no structure is existing in this area, it must
be added at the outermost pre-drilled mounting
hole, directly above the side pad. All other
locations require a backer plate and pipe
spacers (as needed).
G
F
H
Endcap
Drill
Side View
8. Review "Mounting Methods" on page 5.
9. Position top bar in brackets (F). Top bar must be
secured to building in 6 locations (G).
Top bar is pre‑drilled, but other holes may be drilled
in place of these in order to line up with building
structure or to avoid obstacles.
Figure 11
Ce manuel convient aux modèles suivants
1
Table des matières
Manuels Abri populaires d'autres marques

Storage Canopy
Storage Canopy C3340R Manuel utilisateur

Frabill
Frabill ICE HUNTER 195 Manuel utilisateur

Shelters4Less
Shelters4Less SR1588 Manuel utilisateur

Sealey
Sealey Power Products GSS150819SD Manuel utilisateur

Crivit
Crivit 104155 Manuel utilisateur

No Butts Bin
No Butts Bin SR1558-F Manuel utilisateur