LiftLyte Operating Manual - DCNMAN101814 Rev. 3
1. Determine where you will install the LED Light Strips on your runways and where the AC Transformer
Power
Supply will be located (See Figure 3 & Detail A). IMPORTANT: Make sure there will be no
interference with
any accessory components used on the lift. Clean the surface area of the inside
horizontal rail of the lift or wall
of the lube pit using a grease cutting solvent. Allow the surface to dry
completely. Apply the primer stick
mixture in a thin straight line along the complete length of the lift
runway or lube pit wall where the LED Light
Strip will be installed. This will remove any residual oil that
maystill be on the surface. This is critical for the
adhesion of the double stick tape to the metal or
concrete wall (for lube pit application). Repeat on the
opposite runway or wall.
2. Prior to installing the LED Light Strips be certain that the plug end of the Light Strips will be positioned
so the
power cords from the AC Transformer power supply will be able to reach them. It is
recommended to use a
guide when applying the LED Light Strips to keep them straight on the
runways. Remove about a foot of the
protective cover from the double stick tape from the plug end of
one length of light strip. AGAIN –be sure you
are attaching the LED Light Strip so the light shines up.
From the plug end of the LED Light Strip and working back to the terminated end, peel about a foot of
the
protective cover off at a time and attach the LED Light Strip to the thin straight line that was cleaned
in step 4
until the entire LED Light Strip is installed. Press firmly along the entire length of the LED Light
Strips to assure
proper adhesion. Repeat on the opposite runway or wall.
3. The LiftLyte™is designed to accept power from the left or from the right. Position the AC Transformer
Power
Supply (2) where electrical power will be easily available. Attach the plug ends of each Light
Strip to the plug
ends of the AC Power Cord and Transformer. To prevent damage to the plug contacts
be sure to match up the
alignment tabs on the plugs when attaching the power cords to the LED Light
Strips. Use the supplied zip ties
and mounts to secure the wiring as required. Clean the areas where
the tie down points will be located with a
grease cutting solvent and allow it to dry. Additionally clean
those spots with one of the provided primer sticks.
DO NOT APPLY ELECTICAL POWER TO THE
TRANSFORMER AT THIS TIME.
4. Clean the area you have chosen to mount the power supply with a grease cutting solvent and allow it to
dry.
Additionally clean that area with the primer sticks if provided. Remove the protective surface from
the Velcro
strip on the backside of the AC Transformer power supply. Stick the AC Transformer Power
Supply to the
cleaned area and press firmly. DO NOT place the transformer in an area where it can be
damaged by raising or
lowering the lift or by automobile tires or other items. IMPORTANT: Carefully
raise and lower the lift completely
several times to make certain there are no areas where power cords
could get snagged on or crushed by any
parts of the lift.
5. Run an extension cord to the AC Transformer Power Supply. Apply electrical power at this time. Push
the on/off
button on the transformer. The LiftLyte™should activate within 2 seconds. Note that there is
a very slight delay
between activation and illumination of the LED Light Strips.
Figure 3: Total Lift Configuration