• Read this manual completely before attempting installation. Failure to install in accordance
with the installation instructions could void warranty and result in injury or death.
• All permanent electrical connections should be made by a qualied electrician.
• A pressure wire connector, labeled “bonding lug”, is provided on the outside of the unit to
permit connection to a minimum No. 6 AWG (13.3 mm2) solid bonding conductor between
this point and any metal equipment, metal enclosures of electrical equipment, metal water
pipes, or conduit within 5 feet (1.5 meters) of the unit as needed to comply with local
requirements.
• Install at least 5 feet (1.5 meters) from wall of pool. Install ozone generator no less than one
(1) foot above maximum water level to prevent water from contacting electrical equipment.
Install in accordance with the installation instructions.
• Follow all applicable electrical codes.
• DANGER ELECTRIC SHOCK HAZARD: Be sure to turn power OFF and disconnect
from power source before any service work is performed. Failure to do so could result in
serious injury or death.
• The DEL AOP-S must be installed in an outdoor location, or indoors in a forced air ventilated
room, and installed so that the orientation is exactly as shown in Figure 1. Install to provide
water drainage of generator to protect electrical components.
• Mount the DEL AOP-So that it is inaccessible to anyone in the pool. Never attempt any
servicing while unit is wet.
• WARNING Short-term inhalation of high concentrations of ozone and long term
inhalation of low concentrations of ozone can cause serious harmful physiological eects. DO
NOT inhale ozone gas produced by this device.
• DANGER For your safety, do not store or use gasoline, chemicals or other ammable
liquids or vapors near this or any other appliance.
• NOTICE To maintain cosmetic integrity, protect this unit from direct prolonged
sunlight exposure.
• WARNING To reduce the risk of injury, do not permit children to use this product, unless
they are closely supervised at all times.
• WARNING If unit is not operated according to instructions, high dosages of harmful
substances may potentially be released.
• ENVIRONMENTAL NOTICE - Hg-Lamp CONTAINS MERCURY. Manage in accordance with
disposal laws. See: www.lamprecycle.org.
SAVE THESE INSTRUCTIONS!

TABLE OF CONTENTS
SECTION 1 General Information
1A. Description ............................................................................................................1
1B. Specifications ........................................................................................................1
SECTION 2 Installation
2A. Location.................................................................................................................1
2B. Wall Mounting ....................................................................................................2
2C. Plumbing ..............................................................................................................3
2D. Main Power..........................................................................................................5
SECTION 3 Operation
3A. General.................................................................................................................. 6
3B. Initial System Start-Up...................................................................................... 7
3C. System Shut-Down............................................................................................ 7
SECTION 4 Maintenance & Service
4A. System Electro-Mechanical Overview.........................................................7
4B. System Maintenance.........................................................................................8
4C. Ozone Module Service .................................................................................... 9
4D. UV Lamp and Quartz Tube Service.............................................................11
4E. Troubleshooting................................................................................................ 13
Support.......................................................................................................................... 15
DIAGRAMS SHOWN IN THESE INSTRUCTIONS
page 2................................................ MOUNTING LOCATION & NOTATIONS
page 4 ....................................................TYPICAL PLUMBING ARRANGEMENT
page 6................................................................................. FLOW TEST DIAGRAM
page 8.............................................................................................. COMPONENTS
page 10..........................................................OZONE MODULE REPLACEMENT
page 11 ........................................................LAMP & QUARTZ TUBE REMOVAL

1
SECTION 1 General Information
1A. Description
The DEL AOP®-S described in this manual is designed to provide the
benefits of ozonated and UV sterilized water in an environmentally
safe and effective manner. The high quality, specially engineered
components ensure efficient and reliable performance. As a result
of proper use of the DEL AOP®-S, unpleasant effects of traditional
chemical use are virtually eliminated. It is safe and harmless to your
equipment when installed properly.
1B. Specifications
Power Requirements:
110-240V, 50-60 Hz, 1Ø, 0.3 Amp
Water Flow rate:
5-20 GPM
Location Requirements:
Mounting: Wall or post mount in a clean, protected area.
Ambient Temp.: 35°F - 120°F (2°C - 49°C)
2A. Location
Mount in a clean, protected area out of direct sunlight. The unit
must be installed in an outdoor location, or indoors in a forced
air ventilated room, and installed so that the orientation is exactly
as shown in Figure 1. Locate out of reach of sprinklers or drainage
spouts. Mount in the orientation shown in Figure 1, using the two
mounting holes provided inside the enclosure. Allow sufficient
clearance in front for internal access, and above for service of the UV
lamp and quartz tube (13 inches). The DEL AOP-S should be installed
at least one (1) foot above the maximum water level. See Section 2C-3
Check Valve Assembly, for plumbing instructions based on mounting
location.

2
SECTION 2 Installation
1A. Description
The DEL AOP®-S described in this manual is designed to provide the
benefits of ozonated and UV sterilized water in an environmentally
safe and effective manner. The high quality, specially engineered
components ensure efficient and reliable performance. As a result
of proper use of the DEL AOP®-S, unpleasant effects of traditional
chemical use are virtually eliminated. It is safe and harmless to your
equipment when installed properly.
1B. Specifications
Power Requirements:
110-240V, 50-60 Hz, 1Ø, 0.3 Amp
Water Flow rate:
5-20 GPM
Location Requirements:
Mounting: Wall or post mount in a clean, protected area.
Ambient Temp.: 35°F - 120°F (2°C - 49°C)
2A. Location
Mount in a clean, protected area out of direct sunlight. The unit
must be installed in an outdoor location, or indoors in a forced
air ventilated room, and installed so that the orientation is exactly
as shown in Figure 1. Locate out of reach of sprinklers or drainage
spouts. Mount in the orientation shown in Figure 1, using the two
mounting holes provided inside the enclosure. Allow sufficient
clearance in front for internal access, and above for service of the UV
lamp and quartz tube (13 inches). The DEL AOP-S should be installed
at least one (1) foot above the maximum water level. See Section 2C-3
Check Valve Assembly, for plumbing instructions based on mounting
location.
2B. Wall Mounting
1. Wall mount near pool equipment.
2. Refer to Figure 1 to mark the locations for the two mounting
screws.
3. Install screws (or other hardware appropriate for mounting
surface) through the two mounting holes built into the
enclosure.
Figure 1: Mounting Location & Notations
(cover removed)
Ozone Output
Barb
Bonding Lugs
½” Knockout
Main Power
Wires
Water Outlet
Mounting Holes
(2x)
Water Inlet
Allow Vertical Clearance
for UV Lamp Removal
System Active
Indicator
Air Intake
Filter

3
SECTION 2 Installation
2C.Plumbing
2C-1. By-Pass Plumbing
Install by-pass plumbing to DEL AOP-S as shown in Figure 2.
Observe and follow the correct flow directions on all
components.
The variable rate check valve will ensure adequate by-pass flow
through the injector, which will create suction to pull in the
ozone. It will also effectively limit the total by-pass flow to less
than 20 GPM for optimal germicidal UV effectiveness.
The recommended configuration is a dedicated pool return
from the DEL AOP-S. If a dedicated pool return is not possible,
a connection back to the main pool return may be used.
NOTE: For pools equipped with a heater, the by-pass plumbing
tee to the Injector should be installed BEFORE the heater. Any
by-pass that connects back to the main pool return should
occur AFTER all other equipment to avoid collection of gas in
the system and possible failure of pool system components.
2C-2. Pressure Test
If a pressure test is required, it should be performed prior to
installing the check valve assembly tubing connections. Cap
the injector with the ¾” pipe cap provided for the pressure
test. Check inside the AOP-S and all plumbing fittings for leaks.
Repair any leaks before continuing installation.
2C-3. Check Valve Assembly
1. Install tube adapter on the injector.
2. Connect the check valve assembly tubing that is closest to the
check valve to the tube adapter on the injector.
3. Attach the other tubing end of the check valve assembly to the
ozone outlet barb on the AOP-S.
NOTE: If the DEL AOP-S must be mounted below the water
line, the check valve assembly tubing must be run to a point
above the water line. This will prevent water from running back
to the AOP-S when the pool pump is not running, and provides
protection in the event of a failed check valve.

4
SECTION 2 Installation
Figure 2: Typical Plumbing Arrangement (pool with heater)
Variable Rate
Check Valve
Filter
If Equipment is
Above Water
Level, A Check
Valve is Required
Between Injector
& Pool Pump
Dedicated
Pool Return
(Preferred)
Ozone & UV
System
Check Valve
Heater
Main Pool Return
(Optional)
From
Pool
Pump
Injector
(Note Flow
Direction on
Body)

5
SECTION 2 Installation
2C-4. Flow Test
1. Temporarily disconnect tubing from inlet side of the check
valve and attach included flow meter assembly (see Figure 3).
2. Hold the flow meter assembly so that the clear plastic chamber
is vertical and pointed down.
3. Turn on the pool pump as this allows the injector to pull a
vacuum. Under normal operation, the ball in the flow meter
assembly will be floating between the min and max lines. At
a minimum, the ball should indicate at least a small amount
of air flow. If you experience complications, see Section 4E.
Troubleshooting.
4. After the system flow has been verified, remove the flow meter
assembly and reconnect the tubing to the inlet side of the
check valve. Secure all tube connections on the check valve
assembly with tube clamps.
2D. Main Power
Connect the DEL AOP-S to the pool timing clock so that it operates
simultaneously with the pool pump. The circuit must be protected by
a Ground Fault Circuit Interrupter (G.F.C.I.) installed in accordance to
electrical code.
The AOP-S has three wires provided for electrical connection.
Ensure that the AC power source is within the AOP-S input power
specifications and connect as shown on wiring decal: black wire to
Line (or Line 1), white wire to neutral (or Line 2), and green wire to
ground.
A knockout (1/2” trade size) is supplied for appropriate wiring conduit/
fittings per local requirement.
A bonding lug is located on the bottom of the unit for connection to
the pool bonding grid.

6
SECTION 3 Operation
Figure 3: Flow Test Diagram
SECTION 3 Operation
3A. General
To achieve optimal performance from the DEL AOP-S, the pool must
be as clean as possible to start with.
1. Backwash or clean filters one day before starting the AOP-S.
2. Superchlorinate pool water using a chlorine based shock
treatment.
3. Test pool chemistry and adjust pH between 7.4 and 7.6.
Adjust total alkalinity between 80 and 120 ppm.
4. Run pool filtration continuously for 24 hours prior to starting
AOP System.
Flow Meter Assembly

7
SECTION 3 Operation
3B. Initial System Start-Up
1. With the AOP-S cover off, turn on pool pump.
2. Check to ensure the AOP-S system active indicator is on.
3. Check to ensure the AOP-S ozone module indicator is on.
4. Verify that ozone is being pulled into the injector by checking
for bubbles at the return. If an MDV is installed, check the
MDV for bubbles.
5. Verify the above steps for all system conditions (multi-speed
pump settings, etc.)
If you experience complications, see Section 4E. Troubleshooting.
Call 1-800-733-9060 or visit www.c-m-p.com for further assistance.
3C. System Shut-Down
If the system is to be shut-down for an extended period, disconnect
the AOP-S from the power source and disconnect the check valve
assembly tubing from the ozone output barb of the AOP-S. When
winterizing, ensure that all water is drained from the AOP-S.
4A. System Electro-Mechanical Overview
4A-1. DEL AOP-S Components
Ozone Module: The ozone module is fully enclosed and
includes a power indicator light.
UV Lamp: This is housed in a quartz tube, which is sealed
inside of the plumbing.
Ballast: Electronic ballast provides power to the UV lamp.
Flow Switch: Activates the power relay when adequate flow is
established through the AOP-S.
Power Relay: Turns on the ozone module and ballast.
WARNING: Before performing any maintenance, make
sure the DEL AOP-S is disconnected from the power
source, the pool pump is off, and water pressure is
relieved.
Table des matières
Autres manuels CMP Accessoires