AQUATIERE NO SCALE INSTALLATION
Before installing the No scale unit, please ensure you have the correct model with regard to the
water demand and the water hardness/hardness type. Aquatiere can advise if required.
1. INITIAL INSTALLATION CONSIDERATIONS
Observe water byelaws
Ensure there is only one incoming water main
Be aware of condensation issues in warm areas. Recommend that the main vessel
is lagged in pipe lagging to prevent the possibility of this occurring
2. BEST PLACE TO FIT THE UNIT
Close to the rising water main
Recommended not to supply the outside tap
Do not expose to extreme temperatures
3. NON-RETURN VALVE
A single check valve should be fitted
4. DRINKING WATER
As the unit produces drinking water, no separate tap supply is required.
5. COMPONENTS SUPPLIED
Each model has a relevant fitting kit supplied
1” BSP fittings can be supplied on request
6. WATER PRESSURE
Maximum regulated water pressure –4 BAR
Minimum water pressure –1.5 BAR
It is important to fit a pressure reducing valve if pressure is likely to exceed 4 BAR
7. PIPE WORK –COPPER MUST NOT BE USED
Under no circumstances must copper pipe work be used to within 1- metre either
side of the No Scale units. All existing copper pipe should be earth
bonded
Plastic pipes should be used to connect to the No Scale Unit 1- metre either side
to the incoming and outgoing water supply
In new builds or new copper pipe work installations 6- weeks should be allowed to
pass with the water system in full use BEFORE the no scale unit is fitted
8. NON MAINS WATER SUPPLIES
In the event of the water supply being from a well or other natural source,
Aquatiere must be contacted before installation