1 SUNRAC GENERAL REFERENCES
This installation guide contains important information which should be read and understood
before installation and start-up. For safe and reliable operation, the entirety of this guide should
be considered essential reading as safety and operational information is provided in all sections,
not only in the“safety references”section. Both the installer and person responsible for the on-go-
ing operation should read and understand this guide. This guide should always be available at the
installation site. This installation guide refers to the PV-module mounting system SRTP-PM-X only.
The total PV-module area of the PV-modules must not exceed 91 ft². The maximum width of the
PV-modules, including the distances between the PV-modules must not exceed 205 inches and the
height must not exceed 67 inches with the combined maximum surface area of 91 ft². PV-modules
certied to IEC 61215 or UL 1703 must be installed vertically. If the PV modules are not certied to
IEC 61215, UL 1703 then care should be taken to assess the suitability for mounting onto the sub-
structure of the SRTP-PM-X.
The customer must consider the local weather conditions and the suitability of the SRTP-PM-1-X
to operate in these conditions. The Pole Mount structure is designed to perform with a maximum
wind speed of 80mph. The maximum ice thickness is 1inch at maximum windspeed. Snow thick-
ness equivalence of the ice thickness will vary from 2 inch to 12 inchesdepending on local condi-
tions. Where modules are installed in non-equatorial regions thenthe tilt angle of the modules will
reduce the likelihood of high snow thickness.
ALL WARRANTY CLAIMS AGAINST SUNRAC ARE INVALID IF THE SRTPPMX IS INSTALLED IN
INAPPROPRIATE CONDITIONS.
2 ADDITIONAL INSTALLATION ITEMS AND PIPE DIMENSIONS
The Pole Mount SRTP-PM-X mounting structure does not include a main pole or cross beam.
• The cross beam must be supplied separately (not included) Cross Beam Pipe Size Requirement:
is 4.0 inch Nominal, 4.5”inch O.D. Steel Pipe Minimum Wall thickness: Schedule 40 or 0.225 inch
See below for Cross Beam required length.
The main pole must be supplied separately (not included)
• Main Pole Pipe Size Requirement: is 4.0 inch Nominal, 4.5inch O.D. Steel Pipe Minimum
Wall
thickness: Schedule 40 or 0.225 inch Pipe length minimum length: 120.0 inches (10 ft.) See page
6 for depth and hole requirements for main pole.
Cross Beam Lengths Minimum
Lengths shown below. (See 5.3 for exact calculations)
BEAM PM-1 PM-2 PM-3 PM-4 PM-5 PM-6
5” CELL 36” 70” 104” 133” 172” 205”
6” CELL 42” 83” 124” 165” 206” 248”
Overall Dimensions
A – Not to exceed 206 inches per Main Pole Mount Cap
101.6 mm = 48 inches
1640mm = 64.57 inches
3 PARTS LIST
LIST NO.
PART
QUANTITY OF PARTS FOR EACH PM-
1-X
PM-1 PM-2 PM-3 PM-4 PM-5 PM-6
1MAIN POLE, 4.5INCH O.D. 1 1 1 1 1 2(*)
24.5 INCH O.D. POLE CAP 1 1 1 1 1 2(*)
3M10X25 BOLT 3 3 3 3 3 6
4BEAM BRACKET 4 5 6 7 8 9
5CROSS BEAM 1 1 1 1 1 1
6M10 U-BOLT 4 5 6 7 8 9
7M10 WASHER (SPRING & FLAT) 810 12 14 16 18
8M10 NUT 810 12 14 16 18
9PURLIN MOUNT 2 3 4 5 6 7
10 END CLAMP (35,40&50mm PROVID-
ED)
12 12 12 12 12 12
11 MID CLAMP 0 2 4 6 8 10
(*) REQUIRES QTY. 2, 4.0 INCH CAP ASSEMBLIES AND MAIN POLES FOR 5” AND 6” CELLS