4.3.1 Tool installation
(4) Outside and inside the Ex-area (zone 1), in the open air, without any more protective box-
es.
Select the place of installation so that the ventilation in the housing (by way of convection)
between the offset flange plate and slots is not impaired.
Should it nevertheless be necessary to install a protective box, it has to be ventilated so
that the above-stated ventilation is not impaired.
(5) If it is assembled in an enclosed space, it must be well ventilated. The operator shall apply
EN 60 079-10/EN 13 237 as a basis for evaluation.
(6) Not in manhole pits or inspection chambers.
4.3.2 Installation of the monitoring device (LAE)
(4) See documentation 605 602 “Leak Indicating Unit (LAE)”
4.3.3 Installation of the monitoring device ME-MV(-LS)
(4) NOT in potentially explosive areas.
(5) Inside a closed, dry area.
Alternatively: Installation in suitable protective boxes, use an additional external signal or
assignment of the potential free contacts to alarm transmission.
(6) Do not install directly next to a strong heat source.
(7) At least 1 m away from the tool.
(8) NOT in potentially explosive areas.
(9) Inside a closed, dry area.
Alternatively: Installation in suitable protective boxes, use an additional external signal or
assignment of the potential free contacts to alarm transmission.
(10) Do not install directly next to a strong heat source.
(11) At least 1 m away from the tool.
4.4. Installation of the Pneumatic connection lines
(1) Fixed, metallic pipes (e.g. Cu pipe) or sufficiently pressure-resistant plastic pipes in ac-
cordance with section 4.1. (across the entire temperature range), the latter only if the inter-
stitial space is NOT Zone 0.
When using plastic pipes, the underground pipes and overground pipes have to be protec-
tive pipes whose inlets and outlets must be sealed against gas and liquid.
(2) Inside clearance min. 6 mm.
(3) Resistant to the stored product.
(4) Color coding: Measuring line: RED; suction line: WHITE or CLEAR; exhaust: GREEN.
(5) The full cross section must be maintained.
(6) The lines between the interstitial space and leak detector must not exceed 50 m in length.
If the distance is greater than this, a larger cross section must be used. There are special
requirements for the exhaust line, see section 4.4.1.
(7) Condensate traps must be installed at all low points of the connection lines.