PRE-OPERATION CHECKS
Before operating the Nano SP Plus the operator should check that the
working area is suitable for the machine.The ground must bare the
total weight of the Nano SP Plus plus payload (i.e. 550kg + 200kg): a
hard level surface is required e.g. concrete, tiled flooring, adequately
supported laminate flooring, raised access flooring (medium duty). If
unsure check floor specifications before use. The ground should be
free from debris and the operator should beware of holes, hatches,
pits, unprotected manholes, drains etc.
The work area should be cordoned off to prevent inadvertent collision
with other personnel, plant or vehicles working in the area.
Check there are no live electrical cables or conductors within close
proximity to the operator. Check there are no overhead obstructions
likely to cause the operator or the Nano SP Plus danger.
A. Visual Inspection
Carry out a thorough visual inspection of the machine.
Look specifically for any signs of damage to:
1. Handrails, platform deck, cantilever deck.
2. Lifting mast structure, chassis area structure.
3. Pothole mechanism.
4. Wheels and castors, for tyre damage and fixings.
5. Main control cable (curly cable to control arm).
6. All of the key fixings are intact and tight.
7. Check all instruction, information and safety decals are
affixed and are legible.
B. Ensure battery is charged by checking joystick LED light
(green = charged).
C. Ensure hydraulic oil is at correct level. Do not over fill.
Check for hydraulic leaks.
D. Check Nano SP Plus functions are working correctly
before normal use:
1. Check lift functions at ground and in basket by lifting
approx. 0.5m;
2. Check emergency lowering functions at ground
and in basket by lifting 0.5m;
3. Check pothole mechanism and interlock function by lifting 0.5m;
4. Check emergency stop functions at ground and in basket.
5. Lower the platform control arm to the stowed position.
Kneel by the ground control box side of the machine and with
your right hand use the ground controls to raise the platform.
Before moving the platform have your left hand ready over the
platform emergency stop button.When the platform begins to
lift, and only when it is moving, depress the platform emergency
stop button.The movement must stop immediately – if not
contact the technical department.
NB do not switch the joystick on for this procedure.Do not
overstretch yourself i.e. when the platform starts lifting. From the
transport position depress the platform emergency stop after
approx. 100–200mm of vertical travel.Do not allow the platform
to lift more than 300mm before depressing the platform
emergency stop.
Check drive and steer functions work correctly by selecting slow
speed in closed position, followed by fast speed. Check automatic
elevated drive speed is engaged by elevating approx. 0.5m.Then select
drive; the joystick right-hand mode light (orange or green) should be
flashing and drive speed should be slightly slower than slow closed
speed. Check machine brakes when joystick is released.
OPERATING PROCEDURES
7
Courtesy of Crane.Market