BR/BC Series Woodburning Fireplaces
7412944
Framing can be constructed before or after the replace
is set in place, however, most installers build the frame
before setting the replace.
Frame replace with 2 x 4 lumber or heavier materials.
Refer to framing dimensions in Figures 1, 2, 3 or 4 for
basic replace specications.
Framing should be positioned to accommodate
wall covering and replace facing material.
If a circulating replace is to be installed, run the 120
VAC, 60 Hz wiring to the left side of installation. Wiring
must be completed the replace is secured and
nish material applied.
Remove the cover plate and electrical knock-out on the
lower left side of the replace and set aside. Follow the
instructions on Page 10 for proper wiring and installa-
tion of the EB1.
If the fan kit is not being installed with the replace, it
is highly recommended that 120 VAC supply be made
available since someone may elect to install a blower at
a later date.
• Wiring should be installed by a certied
electrician.
• Turn off circuit breaker before wiring models.
Once replace is secured, complete wiring the fan
kit. Remove knockout in the center of the back of the
EB1 and install listed cable clamps. Feed electrical
wire through listed cable clamp leaving approximately
6" (152 mm) of wire exposed through the EB1. Se-
cure listed cable clamp to the wire.
Attach white wire from power source to one (1) wire
of receptacle and secure with nut. Attach black wire
from power source to the other wire of receptacle and
secure with nut. Be sure nuts are secured tightly.
Secure EB1 assembly to inside of electrical box
coverplate using two screws. Attach cover to face of
the EB1 while being careful to position excess wire
completely within the EB1, then attach coverplate to
replace.
Refer to optional Model FK12 fan kit assembly instal-
lation instructions for eld installation.
Since you have already preplanned the chimney run,
you should know exactly how the installation is to be
accomplished — how much pipe is required, the num-
ber of elbows, if any, and type of termination to be used.
REPORT TO YOUR DEALERS ANY
PARTS DAMAGED IN SHIPMENT, SPECIFICALLY
CHECK THE END CONNECTION OF CHIMNEY SEC-
TIONS AND ELBOWS.
Fireplaces may use MHSC Model SK8, or
Model S (three wall) chimney systems. The BR/BC
Series Fireplace will accept the SK8 chimney system as
is; but a TWABR adapter collar is required when using
the Model S (triple wall) chimney system. The installa-
tion procedure described in this manual applies to
the SK8 system. Either chimney system may be used,
but be mixed.
FP555
Insulating between platform and replace.
FP555
Platform, insulation
11/10/97
5/11/99 djt
Hard Flat
Surface
Insulation